Re: [sap-log-mm] Subcontractor Vendor expense posting

Posted by jeffzf
on 08/03/2008 02:45:00 AM


Hi MD,
I tested it, K+L in one item won’t add cost of repair expense into Material
Stock. The repair exp. will be posted into the G/L account you set in the L
item based on the account assignment K.
I don’t know why you have to split two items. Could you pls let us know?
Thanks,
Jeff

On 7/29/08, FICOanalyst via sap-log-mm <sap-log-mm@groups.ittoolbox.com>
wrote:
>
>
>
>
>
> Account Assignment Catagory K used with Line Item Catagory L adds the cost
> of the repair (expense) to the material stock value and changes the material
> cost if its set for variable.
>
> I did end up using K but I split into two line items. One K for the repair
> cost and the other L for the material. As long as I flagged the
> subcontracting line as free, it posted like I wanted.
> —–Original Message—–
> Why don’t input a Account Assignment Category K into PO item, even it is
> valuated-material?
> Thanks,
> Jeff
__.____._

Copyright © 2008 ITtoolbox and message author.
No redistribution.

Related Content

White Papers


In the Spotlight

Business Intelligence Microsoft/SAP Development Manager Needed View job

_.____.__


Leave a Comment so far
Leave a comment



Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s



%d bloggers like this: